Warm Start up
WARM START-UP CHECK LIST
Applicable when HP shaft temperature between 250oC and 350oC
Sl. NO | ACTIVITY | CHECK | TIME * / REMARKS | |
1 | Ensure 6.6KV, 415V, 220V DC, UPS & emergency power supply are available & buses are charged. | |||
2 | Reset under voltage relays on 6.6 kV bus, BTS panel & 415V buses. | |||
3 | Ensure islanding switch is in “OUT” condition (if this unit is selected for islanding) | |||
4 | Ensure all soot blowers are in retracted condition. | |||
5 | Ensure air compressor is running, instrument air & service air systems are charged and backup N2 system is charged. | |||
6 | Shift LPG, H2 & CO2 cylinders (min. 5 LPG, 50 H2 & 20 CO2 cyl.) if generator purged | |||
7 | Ensure coal-handling system is ready & coal is filled in the bunkers | |||
8 | Ensure ash-handling system is ready. | |||
9 | Ensure fire system is ready & pumps are in auto. Jackey pump is running. | |||
10 | Ensure all PTW related to corex system returned & Start N2 purging for corex system as per procedures and check for O2 percentage at both C headers and before trip valve | |||
11 | If O2 before FGTV is less than 0.5 %, open the unit goggle valve after equalizing the pressure before & after the goggle valve. | |||
12 | Boiler drum filling | |||
(a) Ensure DMST levels are normal (> 3.5 mt.). | ||||
(b) Ensure PTWs related to boiler water / steam-touched parts up to MS stop valves & boiler filling system are returned. | ||||
(c) Ensure steam / water-sampling system is lined up & charged. | ||||
(d) Open Boiler SH, RH, ECO vents & start up vents. | ||||
(e) Open ECO recirculation valve (E-20). | ||||
(f) Open low point header drains. Close the main isolation valve to IBD tank. Close SH filling line also. | ||||
(g) Open SH drains at 22 Mt. | ||||
(h) Ensure DM – 34 MIV for deaerator filling of both units are closed. | ||||
(i) Open the chemical dosing valve to boiler filling line. Line up Amine skid to boiler, for chemical dozing. Ensure make-up water to skid. | ||||
(j) Line up and start Boiler fill pump. Start Amine skid pump(s). | ||||
(k) Fill drum level upto (-) 100mm. | ||||
(l) Close the low point drain header drains (both isolation valves). | ||||
13 | Raise fore bay level up to + 100mm. | |||
14 | Starting CW & ACW system | |||
(a) Ensure PTWs related to CW & ACW system are closed. | ||||
(b) Ensure forebay level is above normal (+100mm) | ||||
(c) Line up CW system. Open condenser water box vents & air vents on CW supply line. | ||||
(d) Ensure that CW hot tunnel & cold tunnel is filled through ACW return lines of adjacent unit (when water falls down to CT basin through risers) | ||||
(e) Start CW pump & close the vents after venting. | ||||
(f) Ensure standby CW & ACW pumps are available. | ||||
(g) Open supply valve to ACW suction header (from this unit). | ||||
(h) Charge ACW system slowly, by opening the unit supply valve. | ||||
15 | After ensuring that no PTWs are pending on boiler bottom hopper & DCC, start filling the DCC using CW blow down pump. | |||
16 | (a) Ensure PTWs related to feed water system & Deaerator are closed. | |||
(b) Start Deaerator filling using Boiler fill pump. | ||||
(c) Line up BFPs & feed water line. [At least one BFP suction & discharge valves and HP heaters I/L, O/L & bypass valves should be kept open]. | ||||
(d) Keep feed control station valves in open condition and vent through eco. inlet vent. | ||||
17 | (a) Ensure PTWs related to condenser & hot well makeup systems are closed. | |||
(b) Fill hotwell using DM makeup pump, up to + 100mm. | ||||
18 | Starting of LFO & HFO system | |||
(a) Ensure PTWs related to LFO & HFO system are closed. | ||||
(b) Line up and start LFO transfer pump with 12ksc set point for the recirculation valve. | ||||
(c) Switch on HFO heat tracing at P&H area and at boiler 18mt. | ||||
(d) Line up and start HFO transfer pump. Keep pump recirculation pressure control valve in auto (SP 12ksc). | ||||
(e) Line up & charge one HFO heater from oil as well as steam side (Temp. set point shall be kept as 1100C). | ||||
(f) Open HO – 48 & keep HFO system in short recirculation. | ||||
(g) Ensure standby LFO & HFO transfer pumps are available. | ||||
(h) Line up LPG system & maintain header pressure of 3 ksc. | ||||
19 | Starting of flue gas & air system | |||
(a) Ensure PTWs related to APH, ESP, Flue gas, Secondary air & main boiler are closed. Ensure that manholes & peepholes are closed. | ||||
(b) Ensure DCC has been filled & Seal established. | ||||
(c) Line up and start both APH. Check operation of air motors once. | ||||
(d) Line up secondary air system, flue gas path, and ID & FD fans. | ||||
(e) Line up ESP fields & rapping systems. | ||||
(f) Ensure all stand by LOPs of ID, FD & APH are in standby. | ||||
(g) Start AC scanner air fan after ensuring that emergency air damper is open. | ||||
(h) Start one stream of ID & FD fans. Put furnace pressure control in auto (SP -10mmwc). | ||||
(i) Start Ignitor fan & put damper control in auto (SP 85mmwc) | ||||
20 | Purge & Light up | |||
(a) Ensure that all I&C permits related BMS are returned. Switch ON the power supply for flame scanners. | ||||
(b) Ensure >190 t/hr airflow and Purge the boiler. | ||||
(c) Open IGTV & LOTV and ensure that ignitor pr. after IGTV >0.8 ksc, LFO pr. after trip LOTV >8ksc & atomizing air pr. > 6 ksc. | ||||
(d) Keep ESP rapping motors ON. Ensure that ESP fields are not charged. | ||||
(e) Ensure MS – 1, 2, 3 & 4are closed. | ||||
(f) Light up boiler with 2 LFO guns at AX1. | ||||
21 | Start atleast 4 CT fans | |||
22 | Open HFO return trip valve & HOTV and keep in long recirculation. Close the short recirculation valve (HO 48). | |||
23 | Ensure running of Seal oil, Lube oil & Lift oil system | |||
24 | Start H2 /CO2 filling as per Gen. Gas purging/ filling procedure OP/DC/20/XX | |||
25 | (a) Ensure PTWs related to condensate system are returned. | |||
(b) Line up CEP & condensate line, through LP heaters. | ||||
26 | Ensure that boiler water temp. rise is within 110°c/hr | |||
27 | Take other pair of LFO guns after 30 minutes of light up. | |||
28 | At drum pressure 2 ksc, Close drum, SH, RH & ECO air vents. Start phosphate dozing pump at 2ksc-drum pressure. | |||
29 | Start CEP in recirculation. | |||
(a) Ensure valve gland-sealing header is charged & establish sealing for suction valve of both CEPs. | ||||
(b) Keep pump discharge valves in close and deaerator level control valve in closed condition & LPH-1 & 2 I/L & O/L valves are open & bypass open | ||||
(c) Ensure CEP header vent, recirculation valve are open & in auto. | ||||
(d) Ensure PRDS spray valves are closed. | ||||
(e) Ensure turbine exhaust hood spray valve in auto. | ||||
(f) Start the CEP and keep the other CEP in standby. | ||||
30 | Start BFP in recirculation. | |||
(a) Start lube oil pump & keep in auto. | ||||
(b) Keep BFP discharge valve closed, RC valve open and start booster pump. | ||||
(c) Ensure min. scoop and start BFP. Ensure that LOP stops when lube oil pr is >2.8ksc. Ensure RH & HPBP spray MIV close | ||||
(d) Close warm-up manual isolation valve. | ||||
(e) Keep another BFP in standby with warm up valve open. | ||||
31 | (a) At drum pressure 5 ksc; Close SH header drains and throttle start up vents to 15%. | |||
(b) Give blow down from low point header drains around 3 times & collect the sample. | ||||
32 | (a) Ensure PTWs related to control oil HSU are closed. | |||
(b) Line up Control oil system and start pump. | ||||
(c) Line up & start control oil-circulating pump. | ||||
33 | (a) Ensure PTWs related to HP bypass HSU are closed. | |||
(b) Line up and start HPBP oil pump | ||||
34 | Charge PRDS | |||
(a) Ensure PTWs related to PRDS, MS lines, GS are returned. | ||||
(b) Ensure Deaerator pegging from APRDS is closed. | ||||
(c) Ensure PRDS drains are open. | ||||
(d) Ensure PRDS sprays MIVs are open. | ||||
If external steam is available, | ||||
(e) Slowly open AS-34 to charge unit header from station header | ||||
(f) Maintain PRDS temperature. | ||||
If external steam is not available,( follow after MS line charging) | ||||
(a) Ensure AS-34 inter connection to other unit APRDS is closed. | ||||
(b) Open MOVs AS-31 & AS-21& their MIVs | ||||
(c) Charge slowly APRDS low capacity Line by opening the CV. | ||||
(d) Put PRDS pressure & temperature controls in auto with SP -9 ksc. | ||||
35 | Vacuum pulling | |||
(a) Ensure PTWs related to vacuum system are returned. | ||||
(b) Ensure turbine on barring gear. | ||||
(c) Ensure hotwell level is normal & CEP is running. | ||||
(d) Ensure for valve sealing (LPH-1 normal & emerg. Drain valve, LPH-2 emergency drain valve, LPH-3 emerg. drain valve, vacuum pump suction valves) | ||||
(e) Close Vacuum breaker valve, keep in auto & establish water seal. | ||||
(f) Ensure RH vents & EX-12 are closed. | ||||
(g) Switch ‘ON’ GSC Ex. Fan. | ||||
(h) Line up & Start Vacuum pumps. | ||||
36 | Gland steam header charging | |||
(a) Open Gland steam header drain to atmosphere & also open MAL 81. | ||||
(b) Open partially GS header inlet MIV (full open, If charged from the same unit). | ||||
(c) Open AS-9 fully & its MIV partially (full open, If charged from the same unit). | ||||
(d) Charge gland seal when vacuum is >- 0.3 ksc. | ||||
(e) Control temperature at GS inlet as per curve by throttling AS-9 MIV (if steam is taken from adjacent unit). | ||||
(f) Open GS drain to condenser when vacuum is greater than-0.4 ksc, close atmospheric drain. | ||||
(g) Close CRH pot drain to atoms. & Open CRH-101& keep MAL-81 in auto. | ||||
37 | MS line Charging at drum pressure 10 ksc | |||
(a) Ensure PTWs on turbine stop valves, MS, CRH, HRH& HP/LP & PRDS (if PRDS is charged from same unit) are returned. | ||||
(b) Open MS-101 & MS-102 & it’s before MIVs. | ||||
(c) Open MS strainer drains (MS-105, 106 and before & after MIVs). | ||||
(d) Open drain before APRDS (AS-116). | ||||
(e) Ensure APRDS isolation valves closed. | ||||
(f) Ensure HP bypass is closed. | ||||
(g) Open MIVs of MS-3 & MS-4. | ||||
(h) Charge line by Slowly opening MS-3 & MS-4. | ||||
(i) Close MS-101 & MS-102 & it’s before MIVs. | ||||
(j) Open boiler stop valves MS 1&2 when upstream and downstream pressures are equal. | ||||
(k) Close AS-116. | ||||
(l) Close MS-3, MS-4 & their MIVs. | ||||
38 | Ensure CBD is diverted to IBD tank. | |||
39 | Charge Deaerator pegging slowly from PRDS. | |||
40 | Keep Deaerator & hotwell level controls in auto. | |||
41 | HP-LP bypass charging | |||
(a) Ensure HRH strainer drain (HRH 101,102 & their MIV) are open. | ||||
(b) Ensure CRH drain (CRH 127 & CRH 101) & their MIVs are open. | ||||
(c) Ensure HRH 113, 114, 103, 104 & their MIVs are open. | ||||
(d) Ensure CRH pot drain to atmosphere & RH vent is closed | ||||
(e) Ensure that all MAL drains are open in auto. | ||||
(f) Ensure condenser vacuum is > – 0.9 ksc. | ||||
(g) Open LPBP spray valve around 40%. | ||||
(h) Trip reset LPBP trip. | ||||
(i) Open LPBP valve 5%. Check position feedback | ||||
(j) Open HP bypass slowly (around 3%). Check position feedback | ||||
(k) Open HPBP spray MIV (after watching the raising trend in temp). | ||||
(l) Close start up vents. | ||||
(m) Put HP-LP bypass in auto & keep set point 35 ksc & 8 ksc respectively | ||||
42 | Charge dearator from CRH . | |||
43 | Do APH soot blowing through SCAPH line. | |||
44 | If corex clearance is available,
(a) Ensure corex N2 purging is in progress & O2 in corex sample through vent less than 0.5%. |
|||
(b) Take one pair in X1 elevation after that ensure N2 trip valve closes in auto & remove oil in respective pair | ||||
(c) Take other pair in X1 elevation & remove oil. | ||||
(d) Maintain corex downstream pressure minimum & control the temperature within the limits. | ||||
45 | otherwise | |||
(a) Take one pair of BC guns and change over AX1 to HFO | ||||
(b) Line up Primary air system & start one PA fan. | ||||
(c) Ensure seal air fan is running. | ||||
(d) Line up Mill & Start Mill-A. | ||||
(e) Charge ESP fields at minimum. | ||||
(f) Cut in feeder-A & put temp and airflow control in auto. | ||||
46 | Line up & start second stream of ID, FD fans. | |||
47 | Ensure all standby LOPs of ID, FD & PA are in standby. | |||
48 | Match the currents of FD & ID fans & put ampere bias control in auto. Also keep ID fan draft control in auto (-10mm). | |||
49 | Roll turbine up to 690 rpm as per rolling & synchronization check list OP/F/11/XX. | |||
50 | Put drum level controls in auto. | |||
51 | Start remaining CT fans. | |||
52 | Ensure SADC are in auto. | |||
53 | Close HP bypass and put auto/manual station in auto. | |||
54 | Close MS strainer drains, CRH, HRH drains & MAL valves & MAL valves in auto. | |||
55 | If corex is taken, cut-in one pair in X2 elevation. otherwise | |||
Start second PA fan. | ||||
(a) Ensure fan discharge damper is closed. | ||||
(b) Raise scoop & damper to 30-35% | ||||
(c) Match discharge pressure with running fan discharge pressure. | ||||
(d) Open discharge damper. | ||||
(e) Equally load the fans & put PA header pressure & ampere bias controls in auto. | ||||
Start mill-B & Cut in feeder-B. Put temp and airflow control in auto. | ||||
Ensure DCC is running. | ||||
56 | Increase the load by watching MS-HRH Vs Casing temp. curve | |||
57 | Close Economizer recirculation (E-20) | |||
58 | Ensure SH & RH sprays MIVs are open. | |||
59 | Ensure LPH-1 & 2 are charged & level controls & water side valves in auto | |||
60 | Charge LPH 3 at 25 MW. | |||
(a) Ensure PTW related to LPH-3 is returned. | ||||
(b) Ensure heater is charged from waterside (I/L & O/L valves are open & bypass valve is closed). | ||||
(c) Extraction line drains (EX-125, MAL-54 &126) are open. | ||||
(d) Ensure operating vent is open & shell vent to atmosphere is close | ||||
(e) Open emergency drain & close normal drain. | ||||
(f) Open slowly EX-9 by seeing the heater level & shell pressure. | ||||
(g) After fully opening EX-9 & put it in auto & close EX-125, MAL-54 & 126 & put them in auto. | ||||
(h) Put normal & emergency drains valves in auto (SP-0 & 20 mmwc). | ||||
61 | Start second BFP at 35 MW & ensure third BFP in standby mode. | |||
62 | At 35MW changeover UAT from station. | |||
63 | Charge Deaerator from CRH. | |||
64 | Put MS temperature controls on auto. | |||
65 | If corex is taken, cut-in second pair in X2 elevation | |||
66 | Line up & Charge HPH – 5 at 50 MW | |||
(a) Ensure PTW related to HPH-5 are closed. | ||||
(b) Ensure heater is charged from waterside (I/L &O/L valves are open & bypass valve is closed). | ||||
(c) Open extraction line drains (EX-104, MAL-47 & 106) & ensure operating vent is open & atmosphere vent is close. | ||||
(d) Open fully emergency drain control valve & Keep normal drain control valve in close condition. | ||||
(e) Open slowly block valve EX-11 by seeing the level & shell pressure. | ||||
(f) After fully opening the EX-11, close drains & keep in auto. | ||||
(g) Put HP heater -5 level (normal & emergency) controls in auto. (SP-0 & 20 mm resp.) | ||||
(h) Ensure heater waterside I/L, O/L & bypass valves are in auto. | ||||
67 | Line up & Charge HPH 6 at 60 MW. | |||
(a) Ensure PTW related to HPH-6 are closed. | ||||
(b) Ensure heater is charged from waterside (I/L &O/L valves are open & bypass valve is closed). | ||||
(c) Open EX-128 & its MIV (drain before EX-12) & open operating vent & close atmosphere vent. | ||||
(d) Open emergency drain control valve. | ||||
(e) Ensure control valves of normal & alternate drains are close. | ||||
(f) Open slowly EX-12 from local by seeing the heater level & shell pressure. | ||||
(g) After fully opening the EX-12, put it in remote. Close EX-128 & put in auto. | ||||
(h) Put HP heater -6 level (normal, alternate & emergency) controls, EX-128 in auto. (SP-0, 20& 40 mm resp.). | ||||
(i) Ensure heater waterside I/L, O/L & bypass valves are in auto. | ||||
68 | Deaerator charging from Extraction-4 at 80MW | |||
(a) Open drain traps & its bypass valves before & after EX-4 NRV ‘s & ensure MAL-51 is also open | ||||
(b) Slowly Open EX-10 from DCS. | ||||
(c) After matching upstream & down stream pressure, fully open EX-10 & keep in auto & also close its bypass of traps of the drains. Deaerator pressure operator SP – 3ksc | ||||
69 | If corex is taken, Cut-in first pair in X3 elevation. | |||
70 | Stop second vacuum pump, select the running pump & keep in auto | |||
71 | Ensure SH temperature Controls in auto. | |||
72 | Ensure HP turbine exhaust temperature is < 365 oC. | |||
73 | If corex is taken, Cut-in one pair of X3 elevation otherwise | |||
(a) Start mill-C & cut in feeder-C |
||||
(b) Cut in feeder-C & put temp and airflow control in auto. | ||||
(c) Ensure feeder A & B >50% & scanner intensity > 50 | ||||
(d) Remove oil in AX-1 elevation. (If only coal in service). | ||||
74 | Raise the load as per TSE margins available to 120 MW. | |||
75 | Keep MS temperature control SP as 532 oC. | |||
76 | If corex is taken, Cut-in second pair of X3 elevation. | |||
77 | Put islanding switch in “IN”, if load is more than JVSL complex load (if applicable) | |||
78 | Gradually raise the load to 130MW based on drum water silica | |||
79 | Ensure
CBD tank is taken into service based on silica. |
|||
80 | Ensure ESP fields are in maximum if full coal firing otherwise 1st & 5th fields. | |||
81 | Ensure H2 pressure > 2.9 ksc & purity > 98%. | |||
82 | Put unit in CMC after matching the parameters And ensuring CMC load Ref. Equal to actual load. |